This Practice Note is a supplement to Practice Note 1 ‘Notice’, aimed at highlighting key specific notice provisions under NEC3 & 4 Engineering and Construction Contracts (‘ECC’) and the NEC3 & 4 Engineering and Construction Subcontract (‘ECS’).
Specific Situations Requirement Notices
Contractors and subcontractors should be aware that generally, NEC contracts contain notice provisions in respect of the following situations:
- Compensation Events.
- Early Warning.
- Defects.
- Ambiguities and inconsistencies.
- Illegal and impossible requirements.
- Prevention.
- Termination.
A brief overview these provision is as follows:
NEC3 & 4 (ECC)
Compensation Events
- The Project Manager notifies the Contractor of compensation events arising from an instruction, the issue of a certificate, the changing of an earlier decision, or a correction of an assumption (cl.61.1).
- The Contractor notifies the Project Manager of an event the Contractor believes to be a compensation event that has not been notified by the Project Manager (cl.61.3).
- The Project Manager notifies the Contractor if the Project Manager decides that an event notified by the Contractor is not a compensation event (cl.61.4).
- When requesting a quotation from the Contractor, the Project Manager notifies the Contractor if the Project Manager decides the Contractor failed to issue an early warning notice (cl.61.5).
- If the effects of a compensation event cannot be reasonably ascertained with certainty, then, in an instruction to provide quotations, the Project Manager states any assumptions made by the Project Manager concerning the effects of a compensation event (cl.61.6).
Early Warning
- The Project Manager and the Contractor notify each other as soon as they become aware of any matter which could increase the total of the Prices, delay Completion, delay meeting a Key Date, or impair the performance of the works in use (cl.16.1[NEC3] / cl.15.1[NEC4]).
Defects
- Up to the defects date, the Supervisor and the Contractor notify each other of Defects as soon as they find them (cl.42.2[NEC3] / cl.43.2[NEC4]).
Ambiguities and Inconsistencies
- The Project Manager or the Contractor notify each other as soon as they become aware of any ambiguity or inconsistency in or between the contract documents (cl.17.1).
Illegal and Impossible Requirements
- The Contractor notifies the Project Manager if the Contractor believes the Works Information [NEC3] (or ‘Scope’ as per the NEC4) requires him to do anything illegal or impossible (cl.18.1[NEC3] / cl.17.2[NEC4]).
Prevention
- If an event occurs, which neither Party could prevent, that stops the Contractor from completing the works by the date shown on the Accepted Programme, the Project Manager notifies (instructs) the Contractor on how the event is to be dealt with (cl.19.1).
Termination
- If either Party wishes to terminate the Contractor’s obligation to Provide the Works, the Party wishing to terminate notifies the reason to the Project Manager and the other party (cl.90.1).
NEC3 & 4 (ECS)
Compensation Events
- The Contractor notifies the Subcontractor of compensation events arising from an instruction, the issue of a certificate, the changing of an earlier decision, or a correction of an assumption (cl.61.1).
- The Subcontractor notifies the Contractor of an event the Subcontractor believes to be a compensation event that has not been notified by the Contractor (cl.61.3).
- The Contractor notifies the Subcontractor if the Contractor decides that an event notified by the Subcontractor is not a compensation event (cl.61.4).
- When requesting a quotation from the Subcontractor, the Contractor notifies the Subcontractor if the Contractor decides the Subcontractor failed to issue an early warning notice (cl.61.5).
- If the effects of a compensation event cannot be reasonably ascertained with certainty, then, in an instruction to provide quotations, the Contractor states any assumptions made by the Contractor concerning the effects of a compensation event (cl.61.6).
Early Warning
- The Contractor and the Subcontractor notify each other as soon as they become aware of any matter which could increase the total of the Prices, delay Completion, delay meeting a Key Date, or impair the performance of the works in use (cl.16.1[NEC3] / cl.15.1[NEC4]).
Defects
- Up to the defects date, the Subcontractor and the Contractor notify each other of Defects as soon as they find them (cl.42.2[NEC3] / cl.43.2[NEC4]).
Ambiguities and Inconsistencies
- The Subcontractor or the Contractor notify each other as soon as they become aware of any ambiguity or inconsistency in or between the contract documents (cl.17.1)
Illegal and Impossible Requirements
- The Subcontractor notifies the Contractor if the Subcontractor believes the Works Information [NEC3] (or ‘Scope’ as per the NEC4) requires him to do anything illegal or impossible (cl.18.1[NEC3] / cl.17.2[NEC4]).
Prevention
- If an event occurs, which neither Party could prevent, that stops the Subcontractor from completing the works by the date shown on the Accepted Programme, the Contractor notifies (instructs) the Subcontractor on how the event is to be dealt with (cl.19.1).
Termination
- If either Party wishes to terminate the Subcontractor’s obligation to Provide the Subcontract Works, the Party wishing to terminate notifies the reason to the other party (cl.90.1).
Final Advice
In the management and administration of NEC contracts, parties have the opportunity to act promptly and issue notices in accordance with a wide variety of contractual provisions. This not only aids in avoiding disputes by maintaining communication but also ensures certainty regarding the correct contractual position, which directly contributes to, or even governs, robust commercial management and financial outcomes.